In the last few weeks, we were able to put our own medium-voltage power grid into operation on the Altishofen / Dagmersellen company premises between Logistics Center 1 and 6. The buildings of our neighbor PanGas AG were also integrated.
For the realization countless excavation works, installations of additional transformer stations, rebuildings of electrical main distributions and even a connection under the north-south main axis freeway A2 were necessary.
With the realization of this on-site power grid, we have created the ideal conditions for consistently pursuing our Green Logistics by Galliker strategy. This interconnection ideally enables the integration of our PV systems into the entire system as well as the construction of further e-charging stations for our truck fleet. We will continuously supplement these with new, fully electric vehicles.
Construction work is already in full swing on the second part of our site (Altishofen / Nebikon) for the Areal-Süd power grid.